Tuesday, August 19, 2008

department of Public Works

 On Tue, Aug 19, 2008 at 2:23 PM, Gade, Derek

 

 wrote:

 

 Pointe Communities have executed the agreement with the traffic

 engineer to perform the study. It should be completed mid to late

 Oct.

 

 Thanks,

 Derek

 

 DPW - PDCI

Wednesday, August 13, 2008

department of Public Works

 On Wed, Aug 13, 2008 at 2:01 PM, Gade, Derek

 Derek.Gade@sdcounty.ca.gov

 wrote:

  I'm on it.  You can see Ric's response below as a follow to mine.

  I hope

 to

  hear the status any day now.  I will pass on once I get it.

  Please feel

 free

  to check back in with me by Friday if you have not heard from me.

 

 

  Thanks,

  Derek

 

  DPW - PDCI

department of Public Works

    On Wed, Aug 13, 2008 at 12:51 PM, Gade, Derek

  Derek.Gade@sdcounty.ca.gov wrote:

------------

 

  County approved the scope and etc.  As a result, Ric Williams

  from Pointe Communities has issued the contract to Mr. Darnell,

  Traffic Engineer, to start work.  Ric is awaiting his

  acknowledgement and a start date.

 Thanks,

  Derek

 

  DPW - PDCI

Ric Williams

  From: Ric Williams [mailto:ricwms@pointeinternational.com]

  Sent: Wednesday, August 13, 2008 10:26 AM

  To: Gade, Derek

  Subject: RE: TM 4828-1 Jamacha Blvd revised Traffic Study

 

  Derek

  I have a message in for him today.  I signed and sent the contract

  to him

 on

  Friday with your proposed modifications handwritten in.  He hasn't

 confirmed

  his acceptance of those changes; I don't believe they would pose a

  problem.

  Thanks,

  Ric

 

  Ric Williams

  Pointe & Gosnell Builders

  3130 Bonita Road, Suite 200

  Chula Vista, California 91910

  ricwms@pointeinternational.com

  (619) 691-1800

  (206) 339-7125 (FAX)